Project Timeline

What are the timelines for this project?

ARC-BC began as a two year project designed to provide adequate time for the research, development, testing, and launching of the repository.  At the successful end of that two year period, funding for ARC-BC was extended to allow for future development and maintenance of the collection.

May 2007 – August 2007

  • Research phase
    • Examined existing alternate format repositories
    • Conducted alternate format needs assessment with BC educators
    • Explored options for repository architecture
    • Disseminated information and build project awareness

August 2007 – November 2007

  • Design phase
    • Determined system requirements
    • Designed online repository
    • Designed alternate format production process

November 2007 – March 2008

  • Development phase
    • Programmed online repository
    • Acquired and produced alternate format materials
    • Released information on project pilot and application process

May 2008 – September 2008

  • Population phase
    • Pilot application period
    • Acquired and produced alternate format materials
    • Populated online repository with alternate formats

September 2007 – December 2008

  • Pilot phase
    • Opened access to repository for 8 BC school districts
    • Conducted online and face-to-face training in pilot school districts
    • Built awareness of project in all school districts
    • Opened application for all BC school districts to join ARC-BC Community
    • Reviewed project effectiveness

January 2009 - June 2009

  • Officially launched ARC-BC
  • Added BC school districts to ARC-BC Community throughout January to June period
  • Conducted online and face-to-face training for all interested or involved school districts
  • Conducted ARC-BC Contribute to Collection project in two school districts
  • Conducted year end ARC-BC user survey
  • Began planning and development of ARC-BC v.2.0

January 2009 - June 2010

  • Launch of ARC-BC v.2.0 with improved reporting and community features
  • Addition of remaining BC school districts to ARC-BC Community
  • Continued development of ARC-BC collection – acquisition of new titles and improvement of existing ones
  • Continued online and face-to-face training for all BC educators
  • Further development of web-based support materials for use of ARC-BC alternate formats
  • Extension of ARC-BC Contribute to Collection project